No. | Data | Information |
1 | Village Name | Mbinudita |
2 | Hamlet Name | Wondenu, Tana Karang Hamlet |
3 | RT | 04 |
4 | RW | 02 |
5 | PIC | Mesak Ndena Ngaba |
6 | Number of Families | 7 families |
7 | Number of peoples | 32 Peoples |
8 | Number of Houses | 4 Houses |
9 | Facilities built | 2 cubicle Ferrocement bathing, washing and lavatory |
10 | Point Coordinates | -9.68762, 120.00329 |
Some of the completed sections include:
- proceeded with the installation of 2 roof malls while designing the roof radii.
- casting and installation of zinc 2 sanitary room
- painting 2 sanitation rooms and installing water faucets from reservoirs.
Until now the participation of residents has been very good, local residents have continued to work together according to their respective abilities, old, young, children, women, men all taking part.
The intensity of daily rain is quite high, so that the construction of the toilet in a day cannot be maximized.
A tarpaulin was used as a cover so that the team could still work and the facilities that were built and not yet dry were protected from rainwater.